Information based on query as of Tuesday, July 16, 2024.
Permit Information
Permit NumberFIR11-00567
StatusFinaled
Name BUDGET ELECTRIC
Site Address 3676 E WARM SPRINGS AVE
Project NameBOISE FIRE STATION 15
Customer Number 
ePlanReviewNo
Description
This fire alarm permit is to provide a new FACP for sprinkler system monitoring. Included in this permit scope of work is a remote annunciator, a pull station, monitor modules for the sprinkler system valves, and system smoke detectors instead of single station/multiple station smoke alarms. Notification is not part of this permit scope of work. No HVAC has been indicated on the plans, therefore is not part of this permit scope of work.

Associated building permit: BLD10-02771 Boise Fire Station #15 - To construct a new 11,210 square foot, two story, wood framed and masonry fire station and related site improvements. This building is fully fire sprinkled. First Floor: 8,210 sq. ft. Second Floor: 3,000 sq. ft... All construction per the approved plans and attached comment list. JCM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection7/2/20127/5/20127/6/2012PPASS
DetailsForrest France
Noted correction items verified for completion. Fire alarm work passed acceptance testing. Permit finaled.
INSP-Final Inspection6/27/20126/29/20126/29/2012AFAIL
DetailsTroy Cobbley
The city approved plans had been provided but the review comments and approved small document package was not available. The PIV tamper switch did not work. The sprinkler contractor was not available to test the two flow switches. The sleeping room smoke detectors did not sound a temporal signal as required per NFPA 72 29.3.5. The first floor corridor 104 smoke detector is labeled as Bay 1. As-builts need to be provided showing all of the changes and additions which include an AES panel instead of phone lines, an additional module for the AES trouble (point 17), and the flow switches are shown as tamper switches. A re-inspection fee has been applied.
INSP-Final Inspection6/25/20126/25/20126/25/2012PFAIL
DetailsForrest France
See fire plan review notes item #1 regarding system smoke detectors at the sleeping rooms, tamper switch at the forward flow control valve is wired normally open, revise panel to eliminate the autotest communication error due to AES transmitter.
INSP-Final Inspection6/22/20126/22/20126/22/2012PNR
DetailsForrest France
Johnathan or ###-#### Morgan Phone #: ###-#### Noted items include communication error at the panel, missing approved plans and review comments on site, butterfly valve at the forward flow does not need supervision, post signage at the door to the riser/FACP room, provide record of pre-testing.
FIR-Aging Inspection5/8/20125/8/20125/8/2012 DONE
DetailsForrest France
Construction underway. Site work in progress.
INSP-Conference1/18/20121/19/20121/19/2012ADONE
DetailsForrest France
On site conference regarding location of the FACP and the MP station at the riser room to comply with NFPA 72 and NEC clearance and access guidelines.