Information based on query as of Wednesday, July 24, 2024.
Permit Information
Permit NumberFIR11-00575
StatusFinaled
Name MICRON TECHNOLOGY INC FA
Site Address 8000 S FEDERAL WAY
Project NameB50-R&D EXPANSION BLD
Customer NumberC15044
ePlanReviewNo
Description
This fire alarm permit is to provide a manual fire alarm system in a new building addition. This permit scope of work includes pull stations at every exit, full notification, elevator recall and shunt trip functions, sprinkler system monitoring, a VESDA system, and HVAC system monitoring/shutdown.

Associated building permit: BLD11-00818 Micron Building B50 - R&D Building - To construct a new 111,005 square foot, two story, with 71,855 square foot basement, concrete and steel semiconductor fabrication R & D facility and related site improvements. The first floor level is 89, 435 sq. ft. (60,100 sq. ft. finished and 29,325 sq. ft. unfinished). The second floor is a 21,570 sq. ft. mechanical space (16,170 sq. ft. used and 5,400 square feet future). The basement level (subfab.) has 43,295 sq. ft. finished and 28,560 unfinished. All construction per the approved plans and attached comment list. JCM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection9/18/20129/18/20129/18/2012APASS
DetailsForrest France
Scope of fire alarm work completed, inspections passed. Permit final approved.
INSP-Alarm Testing8/15/20128/15/20128/15/2012PPART
DetailsForrest France
Added heat detectors at the elevator machine room tested okay.
INSP-Final Inspection8/1/20128/1/20128/2/2012APART
DetailsForrest France
SD for elevator recall functions tested acceptable. Need to revise HD locations at the elevator machine room per NFPA 72 21.4.2.
INSP-Final Inspection4/23/20124/23/20124/23/2012APART
DetailsForrest France
Operational test of the fire curtain and acceptance testing per NFPA 80 completed. Re-inspection passed.
INSP-Sprinkler Rough-in4/16/20124/16/20124/19/2012PPART
DetailsForrest France
Regarding relocated SD for door release service at the non-clean link bld 50 side.
INSP-Final Inspection4/17/20124/17/20124/19/2012PPART
DetailsForrest France
INSP-Alarm Testing3/20/20123/20/20123/21/2012PPART
DetailsForrest France
Duct system control valve descriptor and tamper switch at the yard PIV have been provided.
INSP-Alarm Testing3/19/20123/19/20123/19/2012APART
DetailsForrest France
Completed fire sprinkler monitoring test for systems installed to date- system 4,10,2, 8 duct and 8OH flows and tampers. Items noted include; incorrect descriptor at duct system 8 control valve, missing PIV tamper, one incomplete riser manifold, deluge valve for opening protection is unfinished.
INSP-Alarm Testing3/16/20123/16/20123/16/2012PPART
DetailsForrest France
Completed testing for correction notice items dated 3/12. Also tested SD above FATC 5 and zones 1 thru 4 HSSD at the sub fab mechanical. Discussed sprinkler monitoring test and building 24D link testing schedule.
INSP-Alarm Testing3/13/20123/13/20123/16/2012PPART
DetailsForrest France
Completed notification testing for project phase one areas including fabrication, cleanroom, mechanical, dock, and link corridors. Corrections and adjustments include; device location at mechanical room 44, obstructions to coverage at the mechanical deck due to equipment layout, one overspaced appliance at the service area above the photo bay, five TEM labs are below min. dB, insufficient visual coverage at the mechanical catwalks in two areas. Field inspection completed 3/12.
INSP-Alarm Testing3/8/20123/8/20123/9/2012APART
DetailsForrest France
Inspection items completed include; duct detectors at AHU's 5,6,7, SD above FATC at the mechanical level, MAU 1 and 2, and AHU 1 and 2 at the dock area.
INSP-Alarm Testing3/6/20123/7/20123/7/2012APART
DetailsForrest France
Today's inspection included under floor SD's at zones 4 and 5, clean link HSSD's at zones 1,2,3 and 4, HEPA shutdown at zones 1 thru 6 including program operations, duct detectors at mechanical mezzanine 43 and mech. room 44. Initiating device addresses and functionality tested okay. Noted one SD above the FATC in mech. room 44 to be relocated to the deck, MAU's at mech. mezzanine are not ready for shutdown test, discussed locations of duct detectors at the floor level east electrical room.
INSP-Alarm Testing3/5/20123/6/20123/6/2012APART
DetailsForrest France
Devices tested include SD's at panel, extender, underfloor detectors at zones 1,2,3 and 4.
INSP-Alarm Testing2/29/20123/2/20123/2/2012PPART
DetailsForrest France
Completed initial walkthrough and partial testing for fire alarm work at sector 30 and sector 40 sub fab mechanical areas. Notification appliances and pull stations tested okay. Noted address needs assigned at the sw stair MP and accurate descriptor provided for the nw MP. Notification coverage in the fabrication areas may become obstructed as more process equipment is installed. Discussed associated permits for tool monitoring, vesdas, added tamper switches. Elevator control functions are incomplete at this time.
INSP-Conference1/24/20121/26/20121/26/2012ADONE
DetailsForrest France
Regarding completion schedules for additional project related fire alarm permit work.