INSP-Final Inspection | 9/6/2012 | 9/6/2012 | 9/6/2012 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 8/31/2012 | 9/5/2012 | 9/5/2012 | A | FAIL |
Troy Cobbley
|
|
|
NFPA 72 form is not completely filled out.
|
INSP-Final Inspection | 8/31/2012 | 9/4/2012 | 9/4/2012 | A | FAIL |
Troy Cobbley
|
|
|
Repair the PIV, provide notification in the basement dressing rooms, provide activation for the fire/smoke damper in the elevator room wall and provide as-builts which include the address changes, additional devices with revised EOL and voltage calculations.
|
INSP-Final Inspection | 8/29/2012 | 8/31/2012 | 8/31/2012 | A | NR |
Forrest France
|
|
|
Pending corrections.
|
INSP-Final Inspection | 8/29/2012 | 8/30/2012 | 8/30/2012 | A | PART |
Forrest France
|
|
|
Completed initial walkthrough of the basement, first floor and mechanical mezzanine areas. Items noted include; missing lock and labels at the panel breakers, need to relocate the SD at the FACP, provide signage at the door to the FACP room, relocate MP at the riser, include added FSD at the elevator machine room on record drawings, provide missing occupant notification at the pantry locker/dressing room and the shop RR, replace ceiling mount horn at the chiller, need to verify min. dB is met at the storage rooms, visual coverage at the mens and womens dressing rooms 010 and 012 may be insufficient, provide strobe at the NW womens locker WC, provide coverage or a separation door at closet 109, instruction room 161 cd settings revised while on site, a/v at the brides room relocated to the opposite wall, "storage" room 196 will need occupant notification due to change in room use, need to verify dB measurements at the mechanical mezzanine and listing for concealed a/v's on the first floor.
|
INSP-Final Inspection | 8/29/2012 | 8/29/2012 | 8/29/2012 | P | CANC |
Troy Cobbley
|
|
|
overbooked
|
FIR-Aging Inspection | 6/13/2012 | 6/13/2012 | 6/20/2012 | | NR |
Troy Cobbley
|
|
|
work is in progress
|