INSP-Final Inspection | 2/6/2013 | 2/6/2013 | 2/6/2013 | A | PASS |
Forrest France
|
|
|
UG fire supply line permit okay to final.
|
FIR-Aging Inspection | 12/18/2012 | 12/18/2012 | 12/18/2012 | | DONE |
Forrest France
|
|
|
In progress
|
FIR-Aging Inspection | 9/13/2012 | 9/13/2012 | 9/14/2012 | | DONE |
Forrest France
|
|
|
Construction underway, site work in progress.
|
INSP-Sprinkler Rough-in/Hydro | 5/7/2012 | 5/7/2012 | 5/8/2012 | A | PART |
Forrest France
|
|
|
Scope of UG work to date approved.
|
INSP-Supply line flush | 4/17/2012 | 4/18/2012 | 4/19/2012 | A | PART |
Forrest France
|
|
|
UG fire supply line flush completed satisfactory.
|
INSP-Sprinkler Rough-in/Hydro | 2/29/2012 | 2/29/2012 | 2/29/2012 | P | PASS |
Tim Frost
|
|
|
Underground hydro passed, no leakeage.
|
INSP-Sprinkler Rough-in/Hydro | 2/27/2012 | 2/28/2012 | 2/28/2012 | A | FAIL |
Forrest France
|
|
|
UG fire supply line hydrostatic test failed due to visible leakage at the 1/2" valve and pressure loss at the guage.
|
INSP-Sprinkler Rough-in | 2/23/2012 | 2/23/2012 | 2/24/2012 | P | PART |
Forrest France
|
|
|
UG fire supply line from the contractor point of connection to the IBR is approved for bury.
|