INSP-Final Inspection | 5/4/2012 | 5/4/2012 | 5/4/2012 | P | PASS |
Forrest France
|
|
|
UG flush, flow switch test and final walkthrough passed. Permit finaled.
|
INSP-Sprinkler Rough-in/Hydro | 2/28/2012 | 2/29/2012 | 2/29/2012 | P | PASS |
Tim Frost
|
|
|
Rough in was ok. Plastic, was spread over the piping but there was no insulation. One bathroom had changed. There will be a pocket door that separates the area. In essecence, the are will become to small bathrooms which do not require sprinklers.
|
INSP-Supply line flush | 1/26/2012 | 1/26/2012 | 1/26/2012 | P | PART |
Troy Cobbley
|
|
|
Rough to cover the underground passed. Underground flush was not performed.
|
INSP-Supply line flush | 1/19/2012 | 1/20/2012 | 1/20/2012 | P | FAIL |
Troy Cobbley
|
|
|
The underground supply line is not buried deep enough, has been installed as 1 1/2" without the 2" starter and is not a continous run to the riser as shown on the plans.
|