INSP-Final Inspection | 4/24/2012 | 4/24/2012 | 4/26/2012 | P | PASS |
Forrest France
|
|
|
Fire sprinkler permit finaled.
|
INSP-Sprinkler Rough-in/Hydro | 4/23/2012 | 4/24/2012 | 4/24/2012 | A | PART |
Forrest France
|
|
|
Completed satisfactory 24 hr. pneumatic test of the new dry system.
|
INSP-Final Inspection | 4/20/2012 | 4/23/2012 | 4/23/2012 | A | PART |
Forrest France
|
|
|
Begin 24 hr. test of the new dry system at 10:30 AM @41.5psig.
|
INSP-Final Inspection | 4/17/2012 | 4/17/2012 | 4/19/2012 | P | PART |
Forrest France
|
|
|
Final pending 24 hr. test per NFPA 13 2010 24.2.2.1, need to seal or lock the trim valve to the waterflow pressure switch per IFC sec. 903.4 (7).
|
INSP-Sprinkler Rough-in/Hydro | 3/13/2012 | 3/14/2012 | 3/16/2012 | A | PART |
Forrest France
|
|
|
Overhead hydrostatic test at the new dry system completed acceptable. Also discussed seismic bracing and project schedule.
|