INSP-Final Inspection | 5/30/2012 | 5/30/2012 | 5/30/2012 | P | PASS |
Forrest France
|
|
|
Final walkthrough passed. Contractor to provide stock of spare sprinklers of the new type installed at the head box as discussed. Permit finaled.
|
INSP-Sprinkler Rough-in/Hydro | 5/29/2012 | 5/29/2012 | 5/29/2012 | P | PASS |
Troy Cobbley
|
|
|
First floor dry system hydro test passed on the second try. Ken found and fixed the leak.
|
INSP-Sprinkler Rough-in/Hydro | 5/29/2012 | 5/29/2012 | 5/29/2012 | A | FAIL |
Troy Cobbley
|
|
|
Dry system hydro test failed due to visable drop of pressure on the guage. Rescheduled for this afternoon.
|
INSP-Sprinkler Rough-in | 5/15/2012 | 5/15/2012 | 5/15/2012 | P | PART |
Forrest France
|
|
|
OH rough-in partial.
|
INSP-Sprinkler Rough-in/Hydro | 5/11/2012 | 5/11/2012 | 5/11/2012 | A | PART |
Forrest France
|
|
|
OH hydrostatic testing 2nd thru 6th floors completed.
|
INSP-Sprinkler Rough-in/Hydro | 5/10/2012 | 5/10/2012 | 5/10/2012 | P | PART |
Forrest France
|
|
|
Hydrostatic testing for the 2nd floor system completed satisfactory.
|
INSP-Sprinkler Rough-in/Hydro | 5/9/2012 | 5/9/2012 | 5/9/2012 | P | PASS |
Troy Cobbley
|
|
|
Todays inspection was for multiple hydro tests on the 3rd, 4th, 5th and 6th floors. The hydro tests passed.
|