INSP-Final Inspection | 9/27/2012 | 9/27/2012 | 9/27/2012 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled under FIR12-00405
|
FIR-Aging Inspection | 9/27/2012 | 9/27/2012 | 9/27/2012 | | PASS |
Troy Cobbley
|
|
|
Permit finaled under FIR12-00405
|
INSP-Conference | 6/19/2012 | 6/19/2012 | 6/20/2012 | P | DONE |
Forrest France
|
|
|
Jerry phone #: ###-#### or cell ###-####
|
INSP-Sprinkler Rough-in | 5/17/2012 | 5/21/2012 | 5/21/2012 | A | PART |
Forrest France
|
|
|
Insulation tenting for cold cavity protection at the main level completed okay with the exception of four locations. General and sub-contractor finished adjustments today while on site. Overhead install approved for cover. Also discussed obstruction criteria with regard to residential style heads such as light fixtures, finishes, etc.
|
INSP-Sprinkler Rough-in | 5/16/2012 | 5/17/2012 | 5/17/2012 | A | CANC |
Troy Cobbley
|
|
|
Cancel per bruce. Insulation is not yet complete will call for re-inspection next week.
|
INSP-Sprinkler Rough-in | 5/9/2012 | 5/9/2012 | 5/9/2012 | A | PART |
Forrest France
|
|
|
Main level insulation and cover at walls only approved at this time.
|
INSP-Sprinkler Rough-in/Hydro | 5/7/2012 | 5/7/2012 | 5/8/2012 | A | PART |
Forrest France
|
|
|
Main level cover approval pending completion of tenting.
|
INSP-Sprinkler Rough-in | 5/3/2012 | 5/3/2012 | 5/4/2012 | P | PART |
Forrest France
|
|
|
Verified plan modification work. Basement rough-in only okayed for cover. Discussed cold cavity protection issues at the first floor and underground fire supply line work that appears to have been completed without an associated FIR permit or inspection for cover.
|
INSP-Sprinkler Rough-in | 4/18/2012 | 4/19/2012 | 4/19/2012 | A | FAIL |
Troy Cobbley
|
|
|
The piping installation does not match the approved plans. The riser location has been changed. Pipe routing for the main and branchlines has changed. Pipe routing to and in the basement remote area has changed. Pendant head locations have changed. Pendants are supplied from different sources. Alot of additional fittings have been added including four additional elbows in the basement remote area. This does not include the additional fittigns in the supply piping to the remote area. Pendants have been relocated to soffits instead of being installed in the high ceiling areas. Also the wall layout does not match in all locations to the city approved plans. There are areas where hvac duct work is obstructing the pendant heads. Todays inspection was only for the basement area since the main level piping has not been completed yet. Plans need to be resubmitted showing all changes in routing and fitting counts prior to covering by sheet rock. I spoke to Bruce the fitter, Tony Young and with Jerry with Petra about the issues but agreed that I would allow the installation of insulation, for sound proofing, above the piping. This insulation, it was agreed would be installed above the sprinkler piping and would not obstruct my view of the sprinkler piping for the future cover inspection.
|