INSP-Final Inspection | 11/19/2012 | 11/20/2012 | 11/20/2012 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 11/8/2012 | 11/8/2012 | 11/8/2012 | P | PART |
Troy Cobbley
|
|
|
A temporary occupancy was given until the fire sprinkler corrections have been addressed.
|
INSP-Sprinkler Rough-in | 9/27/2012 | 9/27/2012 | 9/27/2012 | P | PART |
Troy Cobbley
|
|
|
Sprinkler rough-in is passed but the sprinkler heads in the corridor as shown on the plans are to be large orfice but as installed are not. I spoke to Jim and he is going to address this issue with Tim Frost.
|
FIR-Aging Inspection | 9/27/2012 | 9/27/2012 | 9/27/2012 | | PASS |
Troy Cobbley
|
|
|
Rough-in inspection scheduled
|
INSP-Sprinkler Rough-in/Hydro | 5/3/2012 | 5/4/2012 | | A | |
Tim Frost
|
|
|
Partial, Ok to cover. Indicated in blue on plans which areas. Passed hydro for mezz
|