INSP-Final Inspection | 8/14/2013 | 8/15/2013 | 8/15/2013 | A | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Final Inspection | 8/13/2013 | 8/14/2013 | 8/14/2013 | A | FAIL |
Troy Cobbley
|
|
|
Basement fire alarm is complete (smoke detector was relocated and pull station lowered for my return trip). First floor fire alrm is complete (except updated as-builts are needed showing one additional in-duct detector). Second floor fire alarm is almost complete (Need to test all duct detectors, add two a/v's as marked on the plans)
|
INSP-Alarm Testing | 8/6/2013 | 8/8/2013 | 8/8/2013 | A | FAIL |
Troy Cobbley
|
|
|
Inspection was for an elevator test but I could not perform the test since the monitoring was not set up yet. I then did a walk through of the first and second floors to verify a/v spacing. I found many a/v's are overspaced most of which were in the restrooms. Many a/v's are missing/have not been installed. The multiple rooms in the Kitchen Area are not built yet and notification has not been installed. The Copy Room has been changed into an office and the a/v deleted. Most of the 15cd a/v in the corridors are mounted above 10' which is too high. Per the installed 12 in-duct detectors have been added. The main elevator, per the contractor, is being "grand fathered" by the state of Idaho and will not be required to have recall as shown on the plans. I did not inspect the basement. Plan modifications are required prior to additional inspections and final sign off.
|
FIR-Aging Inspection | 8/6/2013 | 8/6/2013 | 8/6/2013 | | NR |
Troy Cobbley
|
|
|
work is in progress
|
FIR-Aging Inspection | 5/7/2013 | 5/7/2013 | 5/8/2013 | | NR |
Troy Cobbley
|
|
|
Work is in progess
|
FIR-Aging Inspection | 2/5/2013 | 2/5/2013 | 2/13/2013 | | NR |
Troy Cobbley
|
|
|
|
FIR-Aging Inspection | 9/28/2012 | 9/28/2012 | 9/28/2012 | | NR |
Troy Cobbley
|
|
|
Per Clint the project is currently suspended but might possibly start back up.
|