INSP-Final Inspection | 2/25/2013 | 2/25/2013 | 2/25/2013 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
FIR-Aging Inspection | 2/21/2013 | 2/21/2013 | 2/25/2013 | | PASS |
Troy Cobbley
|
|
|
|
INSP-Sprinkler Rough-in | 11/21/2012 | 11/21/2012 | 11/21/2012 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans for the area in the existing building where the sprinkler piping is ok to cover.
|
INSP-Sprinkler Rough-in/Hydro | 10/22/2012 | 10/22/2012 | 10/22/2012 | P | PASS |
Troy Cobbley
|
|
|
Underground hydro test passed.
|
INSP-Supply line flush | 10/22/2012 | 10/22/2012 | 10/22/2012 | P | CANC |
Troy Cobbley
|
|
|
To be rescheduled per Perly due to United Water not having the underground supply turn on.
|
INSP-Sprinkler Rough-in | 9/20/2012 | 9/20/2012 | 9/20/2012 | P | PASS |
Troy Cobbley
|
|
|
Underground Rough In passed. Remaining piping ok for cover.
|
INSP-Sprinkler Rough-in | 6/20/2012 | 6/21/2012 | 6/21/2012 | A | PASS |
Troy Cobbley
|
|
|
Underground rough in inspection for the riser stub out is passed.
|