INSP-Final Inspection | 8/1/2012 | 8/3/2012 | 8/3/2012 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 7/31/2012 | 8/1/2012 | 8/1/2012 | P | CANC |
Troy Cobbley
|
|
|
Cancel per Jeff since the project related fire alarm permit has not been scheduled.
|
INSP-Final Inspection | 7/30/2012 | 7/31/2012 | 7/31/2012 | A | CANC |
Troy Cobbley
|
|
|
Canceled per Jeff Phone #: ###-####. Fire alarm contractor is not there.
|
INSP-Sprinkler Rough-in/Hydro | 7/2/2012 | 7/2/2012 | 7/2/2012 | P | PART |
Troy Cobbley
|
|
|
Hydro test passed. Sprinkler piping above the lay-in ceiling tile is ok to cover. Plans and hydraulic calculations need to be resubmitted showing the 1 1/4" far main. The plans and calculations show the piping as 1 1/2" piping. Need the pressure relief valve installed.
|
INSP-Sprinkler Rough-in/Hydro | 6/4/2012 | 6/5/2012 | 6/5/2012 | P | PASS |
Troy Cobbley
|
|
|
The overhead hydro test and rough-in of the north canopy dry system passed. The earth quake bracing on the main has not been installed yet.
|
INSP-Sprinkler Rough-in | 6/5/2012 | 6/5/2012 | 6/5/2012 | P | PASS |
Troy Cobbley
|
|
|
This entry is for an inspection called in under FIR12-00175 on 5/17/2012.
The overhead hydro test passed. The sprinkler piping in the Sanctuary/Fellowship areas is ok to cover.
|