Permit NumberFIR12-00223
StatusFinaled
Name AMERICAN FIRE PROTECTION LLC
Site Address 1253 N COLE RD
Project NamePEACE IN JESUS LUTHERAN CHURCH
Customer Number 
ePlanReviewNo
Description
Plan Mod #1 7/09/2012
Based on actual field conditions; the secondary main was 1¼” instead of 1½” that was originally shown. New hydraulic calculations were submitted and are adequate.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection8/1/20128/3/20128/3/2012APASS
DetailsTroy Cobbley
Permit finaled
INSP-Final Inspection7/31/20128/1/20128/1/2012PCANC
DetailsTroy Cobbley
Cancel per Jeff since the project related fire alarm permit has not been scheduled.
INSP-Final Inspection7/30/20127/31/20127/31/2012ACANC
DetailsTroy Cobbley
Canceled per Jeff Phone #: ###-####. Fire alarm contractor is not there.
INSP-Sprinkler Rough-in/Hydro7/2/20127/2/20127/2/2012PPART
DetailsTroy Cobbley
Hydro test passed. Sprinkler piping above the lay-in ceiling tile is ok to cover. Plans and hydraulic calculations need to be resubmitted showing the 1 1/4" far main. The plans and calculations show the piping as 1 1/2" piping. Need the pressure relief valve installed.
INSP-Sprinkler Rough-in/Hydro6/4/20126/5/20126/5/2012PPASS
DetailsTroy Cobbley
The overhead hydro test and rough-in of the north canopy dry system passed. The earth quake bracing on the main has not been installed yet.
INSP-Sprinkler Rough-in6/5/20126/5/20126/5/2012PPASS
DetailsTroy Cobbley
This entry is for an inspection called in under FIR12-00175 on 5/17/2012.

The overhead hydro test passed. The sprinkler piping in the Sanctuary/Fellowship areas is ok to cover.