INSP-Final Inspection | 6/11/2012 | 6/11/2012 | 6/11/2012 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Sprinkler Rough-in/Hydro | 5/29/2012 | 5/29/2012 | 5/29/2012 | P | PASS |
Troy Cobbley
|
|
|
Overhead hydro test passed.
|
INSP-Sprinkler Rough-in | 5/14/2012 | 5/14/2012 | 5/14/2012 | P | PASS |
Troy Cobbley
|
|
|
The sprinkler piping above the hardlids is ok for cover. Myself, Jeremy and the job superintendant discussed possible sprinklers being blocked by fixtures/valances. Jeremy is going to investigate. Another rough-in inspection will be required when the T-bar is installed. Upright sprinkler coverage will be required in the stock room. Bracing will be required for sprig ups over 4'.
|