Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberFIR12-00246
StatusFinaled
Name TREASURE VALLEY FIRE PROTECTION
Site Address 3550 W AMERICANA TERR
Project NameRIVERVIEW REHABILITATION
Customer Number 
ePlanReviewNo
Description
The Fire Sprinkler Scope of work consists of a wet and dry system for a skilled nursing facility. New 6” underground was installed under permit FIR11-00680. The underground supplies a 4” header with a backflow preventer. The residence wings are gridded and utilized CPVC as well as steel piping. A tree system layout of steel piping supplies the central area. The dry system uses attic sprinklers BB and AP. Construction is a mixture of standard trusses, composite wood joist and open wood joist. The composite wood joists are to be filled with noncombustible insulation, and fire stopped into 1603 spaces.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection2/11/20132/12/20132/12/2013APASS
DetailsForrest France
Final walkthrough completed satisfactory. Fire sprinkler permit finaled.
INSP-Final Inspection2/11/20132/11/20132/11/2013PPART
DetailsForrest France
Riser supervision tested satisfactory, low air switch adjusted while on site, forward flow completed.
INSP-Sprinkler Rough-in/Hydro12/7/201212/7/201212/7/2012PPART
DetailsForrest France
Concluded satisfactory air test of the new dry system with no pressure loss at the guage. Also finished hydrostatic testing of the wet system.
INSP-Sprinkler Rough-in/Hydro12/6/201212/6/201212/7/2012PPART
DetailsForrest France
Begin 24 hr. air test 12/5 12:30 PM @ 40psig. on the new dry system.
INSP-Sprinkler Rough-in12/3/201212/3/201212/3/2012PPASS
DetailsTroy Cobbley
See the city approved drawings for locations marked in red where sprinkler piping can be covered.
INSP-Sprinkler Rough-in11/19/201211/19/201211/19/2012APART
DetailsForrest France
Okay to cover hard lid ceilings at the common areas west wing.
INSP-Sprinkler Rough-in11/8/201211/8/201211/8/2012PPART
DetailsForrest France
Pendent heads at the sheetrock ceilings in the physical therapy room are approved for cover.
INSP-Sprinkler Rough-in10/24/201210/24/201210/24/2012PPART
DetailsForrest France
Heads at drop ceilings in the east and west wing corridors okay for cover, heads in sheetrock ceilings at the dining area restrooms and soffits completed to date also approved for cover.
INSP-Sprinkler Rough-in9/10/20129/11/20129/11/2012APART
DetailsForrest France
Pendent heads at the nurse station 135 sheetrock ceiling are approved for cover.
INSP-Sprinkler Rough-in8/29/20128/29/20128/30/2012PPART
DetailsForrest France
Okay to cover pendent and SW heads above the sheetrock ceilings at the east wing resident rooms.
INSP-Sprinkler Rough-in8/27/20128/27/20128/27/2012APART
DetailsForrest France
Dry system at the front entry vaults passed rough-in inspection.
INSP-Sprinkler Rough-in/Hydro8/24/20128/24/20128/24/2012PPART
DetailsForrest France
Hydrostatic test of the new dry system passed after repairs made.
INSP-Sprinkler Rough-in8/23/20128/23/20128/23/2012PPART
DetailsForrest France
Regarding dry system hydrostatic test and 12 missing dry SW heads.
INSP-Sprinkler Rough-in8/13/20128/13/20128/13/2012APART
DetailsForrest France
Non-sprinklered overbuilds at the east wing verified for insulation fill to meet allowable exceptions per NFPA.
INSP-Sprinkler Rough-in7/31/20127/31/20127/31/2012PPART
DetailsForrest France
Overhead rough-in at the kitchen area as marked and dated on stamped plans okayed.
INSP-Sprinkler Rough-in7/16/20127/16/20127/16/2012PPART
DetailsForrest France
Completed inspection for tenting at the east wing. Noted three areas in need of adjustment- notified general contractor. Also discussed FDC location to comply with IFC section 912 conditions.
INSP-Sprinkler Rough-in7/12/20127/12/20127/12/2012PNH
DetailsForrest France
Arrived at the jobsite at 4:30- Gate locked, no access
INSP-Sprinkler Rough-in7/2/20127/2/20127/2/2012PPART
DetailsForrest France
Tenting at the wet system lines west wing only approved as noted.
INSP-Sprinkler Rough-in6/19/20126/19/20126/20/2012APART
DetailsForrest France
Regarding exceptions allowed for non-sprinklered concealed spaces.
INSP-Sprinkler Rough-in6/15/20126/15/20126/15/2012PPART
DetailsForrest France
East wing dry and wet system rough-in inspection as annotated and dated on stamped plans okayed. One seismic brace at the 3" dry main needs relocated per plan.
INSP-Sprinkler Rough-in/Hydro6/4/20126/5/20126/5/2012APART
DetailsForrest France
Overhead rough-in inspection for the west wing dry system completed. Need to verify insulation fill at two areas per plan for allowable exceptions, inspectors test connection and the last attic head east end are not yet installed. Ref. plans for dated annotations.
INSP-Sprinkler Rough-in6/4/20126/4/20126/4/2012PPART
DetailsForrest France