Information based on query as of Tuesday, July 16, 2024.
Permit Information
Permit NumberFIR12-00285
StatusFinaled
Name TREASURE VALLEY FIRE PROTECTION
Site Address 546 N MILWAUKEE ST
Project NameShell Work - No Tenant
Customer Number 
ePlanReviewNo
Description
The fire sprinkler scope of work consists of adding, relocating and deleting sprinklers to provide shell protection until a new tenant occupies the space. The existing system is a 3”x2½”x1½” grid.

FIELD INSPECTOR: All sprinklers to be the same temperature and same response type.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection8/27/20128/27/20128/27/2012PPASS
DetailsTroy Cobbley
Permit finaled. The hydro test and head change out will be addressed under the tenant permit.
INSP-Sprinkler Rough-in6/22/20126/22/20126/22/2012PPASS
DetailsTroy Cobbley
Rough-in passed. Piping placement, on the plans, does not necessarily match the actual installation. Piping needs to be hydro tested. Also per the plans the temp. and responce needs to match on all heads which it does not. There are 165 heads installed at the south/front of the project. The rest of the heads are 200 degree.