INSP-Final Inspection | 9/19/2012 | 9/19/2012 | 9/20/2012 | P | PASS |
Forrest France
|
|
|
Fire sprinkler permit finaled. Forward flow completed with two outlets (3"@755/ 2.5"@694).
|
INSP-Final Inspection | 9/12/2012 | 9/13/2012 | 9/13/2012 | P | NR |
Forrest France
|
|
|
Foward flow test did not meet system design.
|
INSP-Sprinkler Rough-in/Hydro | 8/7/2012 | 8/7/2012 | 8/27/2012 | P | PART |
Forrest France
|
|
|
Overhead hydrostatic test completed satisfactory.
|
INSP-Sprinkler Rough-in | 8/9/2012 | 8/9/2012 | 8/9/2012 | A | PART |
Forrest France
|
|
|
Okay to cover grid ceilings at the second floor offices, storage, hall and stairway areas.
|
INSP-Sprinkler Rough-in | 8/3/2012 | 8/6/2012 | 8/8/2012 | A | PART |
Forrest France
|
|
|
Overhead rough-in at the hanger area passed.
|
INSP-Sprinkler Rough-in | 7/10/2012 | 7/10/2012 | 7/10/2012 | P | PART |
Forrest France
|
|
|
Completed rough-in inspection for the lower office area only. Note* work appears satisfactory however plans do not match installation- cover approval is conditional upon plan resubmittals.
|