INSP-Final Inspection | 11/29/2012 | 11/29/2012 | 11/29/2012 | P | PASS |
Forrest France
|
|
|
Final walkthrough and inspection completed. Forward flow passed. Fire sprinkler permit finaled.
|
INSP-Final Inspection | 11/28/2012 | 11/28/2012 | 11/29/2012 | P | NR |
Forrest France
|
|
|
Final pending project related fire alarm testing for riser supervision. Also need to complete forward flow test.
|
INSP-Sprinkler Rough-in/Hydro | 11/28/2012 | 11/28/2012 | 11/29/2012 | P | PART |
Forrest France
|
|
|
Overhead hydrostatic test completed satisfactory. Need to add baffles per approved plan.
|
INSP-Sprinkler Rough-in | 11/13/2012 | 11/14/2012 | 11/14/2012 | A | PART |
Forrest France
|
|
|
Existing storeroom and stock area fire sprinkler work passed overhead rough-in inspection. Okayed for ceiling cover- see plans for dated annotations.
|
INSP-Sprinkler Rough-in | 11/8/2012 | 11/13/2012 | 11/13/2012 | A | CANC |
Troy Cobbley
|
|
|
Cancel per mike Phone #: ###-####
|
INSP-Sprinkler Rough-in | 10/29/2012 | 10/30/2012 | 10/31/2012 | P | PART |
Forrest France
|
|
|
Overhead rough-in at the upper warehouse passed- see plans for dated annotations.
|