INSP-Final Inspection | 10/4/2012 | 10/5/2012 | 10/5/2012 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled.
|
INSP-Sprinkler Rough-in/Hydro | 7/24/2012 | 7/24/2012 | 7/24/2012 | P | PASS |
Troy Cobbley
|
|
|
Hydro test passed for the overhead systems.
|
INSP-Sprinkler Rough-in | 7/23/2012 | 7/24/2012 | 7/24/2012 | A | PASS |
Troy Cobbley
|
|
|
Tenting is passed. Sprinkler piping can be covered.
|
INSP-Sprinkler Rough-in | 7/19/2012 | 7/20/2012 | 7/20/2012 | P | PASS |
Troy Cobbley
|
|
|
Sprinkler rough-in passed. One pendant head still needed to be installed. One pendant head shown to be installed in the main level restroom has not been installed and doesn't need to be based on NFPA 13R 6.6.2. Piping can not be covered until the insulation/tenting is completed and inspected. An additional inspection will be required for this.
|