INSP-Final Inspection | 1/31/2013 | 1/31/2013 | 1/31/2013 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Sprinkler Rough-in/Hydro | 1/25/2013 | 1/25/2013 | 1/25/2013 | P | PASS |
Troy Cobbley
|
|
|
Overhead hydro passed
|
INSP-Sprinkler Rough-in | 12/12/2012 | 12/12/2012 | 12/12/2012 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans for locations where piping can be covered. I posted a stop work order on the front of the building due to hardlids continuing to be installed prior to a sprinkler rough-in inspection. I had a previous conversation with contractor about this. Stop work order states "Stop all sheet rock that is covering sprinkler piping. Cover inspection is required".
|
INSP-Supply line flush | 11/14/2012 | 11/14/2012 | 11/14/2012 | P | PASS |
Troy Cobbley
|
|
|
The underground supply line flush passed.
|
INSP-Sprinkler Rough-in | 11/13/2012 | 11/14/2012 | 11/14/2012 | A | PASS |
Troy Cobbley
|
|
|
The entry lobby sprinkler piping is ok to re-cover. Tim Frost approved as-builts have been marked up by me for location and have been left on the job site with the sprinkler fitter.
|
INSP-Sprinkler Rough-in | 11/8/2012 | 11/8/2012 | 11/8/2012 | P | CANC |
Troy Cobbley
|
|
|
Cancel per Perly Daniel
|
INSP-Sprinkler Rough-in | 11/7/2012 | 11/7/2012 | 11/7/2012 | P | FAIL |
Troy Cobbley
|
|
|
Joe Snyder was requesting a rough-in inspection for the main lobby entry area. I could not give approval due to the piping arrangement not matching the approved plans. The BB heads have been removed and standard coverage upright heads installed. Also the piping has been covered by sheet rock without approval. I spoke to the job site superintendant about a possible stop work order if covering pipe prior to an inspection continued. He agreed that it would not happen again. Plans need to be resubmitted showing the piping changes in all areas and access provided for the following inspection.
|
INSP-Sprinkler Rough-in | 10/17/2012 | 10/17/2012 | 10/17/2012 | P | PASS |
Troy Cobbley
|
|
|
The sprinkler piping in the drive thru canopy can be covered.
|
INSP-Sprinkler Rough-in | 9/19/2012 | 9/20/2012 | 9/20/2012 | P | CANC |
Troy Cobbley
|
|
|
Underground Rough-in. Scott Carter is the contact at ###-####. Phone #: ###-#### >> Inspection requested via web by Kindel de Leon Inspection cancelled from web by: Kindel de Leon
|