INSP-Final Inspection | 11/13/2012 | 11/14/2012 | 11/14/2012 | P | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Alarm Testing | 11/7/2012 | 11/8/2012 | 11/8/2012 | A | PART |
Troy Cobbley
|
|
|
A temporary occupancy was given until the fire alarm permit/correction issues have been addressed.
|
INSP-Final Inspection | 11/5/2012 | 11/6/2012 | 11/6/2012 | P | CANC |
Troy Cobbley
|
|
|
No testing was performed due to the plans needing resubmitted. I also noted door magnets that have been installed within the past week that are not connected to the fire alarm system as required per IFC 1008.1.4.4.
|
INSP-Final Inspection | 10/29/2012 | 10/29/2012 | 10/29/2012 | P | FAIL |
Troy Cobbley
|
|
|
All items tested except for the smoke detector over the main facp, duct smoke detectors and all notification items. Plans need to be resubmitted showing the correct NAC panels installed, audio/visuals have been added, candellas have been changed, audio/visual devices are overspaced and some are mounted too high. The manual pull station is mounted too high as well. Signals were verified through the Peak Alarm guard at the gate.
|