INSP-Final Inspection | 10/31/2012 | 11/1/2012 | 11/1/2012 | A | PASS |
Forrest France
|
|
|
Final inspection passed. Fire sprinkler permit final approved.
|
INSP-Final Inspection | 10/19/2012 | 10/22/2012 | 10/30/2012 | A | PART |
Forrest France
|
|
|
Completed final system walkthrough. Verified sprinkler monitoring, forward flow test finished. Items noted include; missing escutcheons, travel caps, head cages at uprights below 7', need to install intermediate temp heads at the skylights (8 locations), caps at end mains to remain accessible. Note- some items finished while on site.
|
INSP-Sprinkler Rough-in | 10/15/2012 | 10/16/2012 | 10/30/2012 | P | PART |
Forrest France
|
|
|
See dated plan annotations
|
INSP-Sprinkler Rough-in/Hydro | 10/19/2012 | 10/19/2012 | 10/22/2012 | A | PEND |
Forrest France
|
|
|
|
INSP-Sprinkler Rough-in | 10/15/2012 | 10/15/2012 | 10/16/2012 | P | PART |
Forrest France
|
|
|
Okay to cover pendent heads at the seafood area grid ceilings and the second floor corridor sheetrock ceiling.
|
INSP-Sprinkler Rough-in | 10/9/2012 | 10/9/2012 | 10/9/2012 | P | PART |
Forrest France
|
|
|
Pendent heads at the grid ceilings main level including the kitchen and service counter areas okay for cover.
|
INSP-Sprinkler Rough-in | 9/26/2012 | 9/26/2012 | 9/26/2012 | P | PART |
Forrest France
|
|
|
Grid ceiling areas on the second floor and sheetrock soffit at the sw main level okay for cover.
|
INSP-Sprinkler Rough-in | 9/17/2012 | 9/17/2012 | 9/17/2012 | A | PART |
Forrest France
|
|
|
Branchline piping to SW heads at the storefront canopy okayed for cover.
|
INSP-Sprinkler Rough-in | 9/13/2012 | 9/14/2012 | 9/14/2012 | A | PART |
Forrest France
|
|
|
Inspection for cover at the plan modification area okay for cover. Completed shell rough-in inspection, noted areas to maintain coverage between uprights and full height walls.
|
INSP-Sprinkler Rough-in/Hydro | 9/6/2012 | 9/7/2012 | 9/7/2012 | A | PASS |
Troy Cobbley
|
|
|
The sprinkler piping clouded in red on the modified plans is ok to cover given todays date. I noted that the 4" main, as marked on the plans has additional elbows which may require another plan modification to verify hydraulic calculations.
|
INSP-Conference | 8/28/2012 | 8/29/2012 | 9/5/2012 | A | DONE |
Forrest France
|
|
|
On site conference with contractor regarding sprinkler coverage at exterior canopies to meet the guidelines and requirements of NFPA 13 2010 sections 8.15.7.1, 8.15.7.2, 8.15.7.3, and 8.15.7.5. Any alternate proposals or methods to these conditions must be approved by the fire code official per IFC 2009 104.9.
|
INSP-Sprinkler Rough-in | 8/28/2012 | 8/29/2012 | 8/29/2012 | A | PART |
Forrest France
|
|
|
Overhead work at the second floor elevator machine room and four office rooms okayed for ceiling cover, also approved rough-in at the new 2" branch line and drops to the produce cooler and ceilings in the specialty area.
|
INSP-Conference | 8/27/2012 | 8/29/2012 | 8/28/2012 | A | CANC |
Troy Cobbley
|
|
|
Would like to review permit comments in regards to field verification of exterior canopy protection. Please call cell phone with time frame. Thanks, Jeff Packham. Phone #: ###-#### >> Inspection requested via web by Jeff Packham Inspection cancelled from web by: Jeff Packham
|