INSP-Final Inspection | 8/26/2013 | 8/27/2013 | 8/27/2013 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
FIR-Aging Inspection | 6/27/2013 | 6/27/2013 | 6/28/2013 | | DONE |
Troy Cobbley
|
|
|
work is in progress
|
FIR-Aging Inspection | 2/19/2013 | 2/19/2013 | 2/20/2013 | | NR |
Troy Cobbley
|
|
|
work is in progress
|
INSP-Sprinkler Rough-in/Hydro | 9/28/2012 | 10/1/2012 | 10/1/2012 | A | CANC |
Troy Cobbley
|
|
|
Need an Underground Hydro inspection 1st thing in the morning if possible - Brian Dunham is the contact at 570.0497 Phone #: ###-#### >> Inspection requested via web by Kindel de Leon Inspection cancelled from web by: Scott Carter II
|
INSP-Sprinkler Rough-in | 9/26/2012 | 9/27/2012 | 9/27/2012 | P | PASS |
Troy Cobbley
|
|
|
Underground supply line is ok to cover. I noted that two additional (four total) 45 degree fittings have been installed and will need to be included in the hydraulic calculations for the overhead sprinkler system.
|