INSP-Final Inspection | 12/17/2013 | 12/17/2013 | 12/18/2013 | P | PASS |
Forrest France
|
|
|
|
INSP-Final Inspection | 12/12/2013 | 12/13/2013 | 12/13/2013 | A | PART |
Forrest France
|
|
|
Refer to fire plan review notes item # 7 regarding isolation valves. Also noted missing caps at several locations.
|
INSP-Final Inspection | 11/27/2013 | 12/2/2013 | 12/3/2013 | A | PART |
Forrest France
|
|
|
Missing valve caps at several locations.
|
INSP-Final Inspection | 11/19/2013 | 11/22/2013 | 11/26/2013 | A | NR |
Forrest France
|
|
|
Mike B is the contact. Thanks Phone #: ###-#### >> Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 7/30/2013 | 7/31/2013 | 7/31/2013 | A | PART |
Forrest France
|
|
|
OH hydrostatic test of both standpipes completed satisfactory.
|
FIR-Aging Inspection | 6/28/2013 | 6/28/2013 | 6/28/2013 | | DONE |
Forrest France
|
|
|
Site work in progress
|
INSP-Sprinkler Rough-in/Hydro | 3/27/2013 | 3/29/2013 | 3/29/2013 | P | PART |
Forrest France
|
|
|
For OH hydrostatic test up to the 10th floor.
|
INSP-Sprinkler Rough-in | 3/5/2013 | 3/5/2013 | 3/5/2013 | A | PART |
Forrest France
|
|
|
Standpipe to within one floor of secured decking is installed.
|
INSP-Sprinkler Rough-in | 2/15/2013 | 2/19/2013 | 2/21/2013 | A | PART |
Forrest France
|
|
|
Partial rough in for standpipe. Mike B is the contact. Thanks Phone #: ###-#### >> Inspection requested via web by Stan Beus
|