INSP-Final Inspection | 2/12/2014 | 2/13/2014 | 2/13/2014 | P | PASS |
Forrest France
|
|
|
Fire sprinkler permit finaled.
|
INSP-Final Inspection | 2/11/2014 | 2/12/2014 | 2/12/2014 | P | FAIL |
Forrest France
|
|
|
Missing trim and finishes at several locations, damaged SW head at the west stair 3rd floor, non-functional high/low air switch. Not ready for final.
|
INSP-Sprinkler Rough-in/Hydro | 2/3/2014 | 2/3/2014 | 2/3/2014 | A | PART |
Forrest France
|
|
|
OH hydrostatic test of the wet system completed and passed.
|
INSP-Sprinkler Rough-in/Hydro | 2/3/2014 | 2/3/2014 | 2/3/2014 | A | PART |
Forrest France
|
|
|
OH hydrostatic test of the new dry system passed.
|
INSP-Sprinkler Rough-in/Hydro | 1/31/2014 | 1/31/2014 | 1/31/2014 | P | NH |
Forrest France
|
|
|
PSI reduced prior to completion of test.
|
INSP-Sprinkler Rough-in/Hydro | 1/17/2014 | 1/21/2014 | 1/17/2014 | P | CANC |
Forrest France
|
|
|
Please call Colton 30 mins prior Phone #: ###-#### >> Inspection requested via web by Jacci Hunt Inspection cancelled from web by: Jacci Hunt
|
INSP-Sprinkler Rough-in/Hydro | 12/30/2013 | 12/30/2013 | 12/30/2013 | P | PART |
Forrest France
|
|
|
UG fire supply line hydrostatic test passed.
|
INSP-Sprinkler Rough-in/Hydro | 12/23/2013 | 12/23/2013 | 12/23/2013 | P | NR |
Forrest France
|
|
|
Incomplete work at the dry system, 1st and 2nd floor wet systems. UG fire supply line unable to maintain 200 psig.
|
INSP-Sprinkler Rough-in/Hydro | 12/12/2013 | 12/16/2013 | 12/17/2013 | P | PART |
Forrest France
|
|
|
Noted corrections at dry system, discussed OH and UG hydrostatic test schedule.
|
INSP-Supply line flush | 12/12/2013 | 12/16/2013 | 12/17/2013 | A | PART |
Forrest France
|
|
|
Please call Colton 30 mins prior Phone #: ###-#### >> Inspection requested via web by Jacci Hunt
|
INSP-Sprinkler Rough-in | 11/25/2013 | 11/26/2013 | 11/26/2013 | A | FAIL |
Forrest France
|
|
|
Inspection for cover at the second floor (3rd level) failed due to installation not matching plans- calc area included. Provide plan modification for changes prior to approval for cover.
|
INSP-Sprinkler Rough-in | 9/18/2013 | 9/19/2013 | 9/23/2013 | A | NR |
Forrest France
|
|
|
|
INSP-Sprinkler Rough-in/Hydro | 9/20/2013 | 9/23/2013 | 9/23/2013 | A | NR |
Forrest France
|
|
|
Rough-in inspection at second floor incomplete due to changes in floorplan, main and branchline routing. Tie-ins at the east stairway unfinished. Need to provide stamped resubmittals reflecting actual pipe routing and accurate floorplan prior to approval for cover.
|
FIR-Aging Inspection | 4/4/2013 | 4/4/2013 | 4/5/2013 | | DONE |
Forrest France
|
|
|
Site construction in process
|