INSP-Final Inspection | 2/4/2013 | 2/6/2013 | 2/6/2013 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 11/19/2012 | 11/20/2012 | 11/20/2012 | A | FAIL |
Troy Cobbley
|
|
|
The zone 6 still did not report within the required 90 seconds. I then verified the actual time on a general alarm and found that it did not report to the monitoring station within the 90 seconds either. The fire alarm system shall meet current timing requirements as per NFPA 72. A re-inspection fee has been applied to this job for any more inspections.
|
INSP-Final Inspection | 11/19/2012 | 11/19/2012 | 11/19/2012 | P | FAIL |
Troy Cobbley
|
|
|
The duct smoke detectors on zone 6 still are not reporting to the monitoring station.
|
INSP-Final Inspection | 11/16/2012 | 11/16/2012 | 11/16/2012 | P | PART |
Troy Cobbley
|
|
|
A temporary occupancy was given with Scott Arellano's permission until the correct programming of the duct smoke detectors is accomplished with the monitoring company. All other items have been corrected. The hvac units had not previously been wired for shut down but are now.
|
INSP-Final Inspection | 11/15/2012 | 11/16/2012 | 11/16/2012 | A | FAIL |
Troy Cobbley
|
|
|
The fire alarm control panel only has one phone line, monitoring is not set up correctly (no alarm or supervisory signals were received), hvac units did not shut down upon detection of smoke and as-builts are needed showing the additional tamper switch as well as the smoke detector above the ceiling.
|