INSP-Final Inspection | 7/9/2013 | 7/10/2013 | 7/10/2013 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled by tim frost on 2/22/13
|
FIR-Aging Inspection | 7/9/2013 | 7/9/2013 | 7/9/2013 | | PASS |
Troy Cobbley
|
|
|
|
INSP-Final Inspection | 2/21/2013 | 2/22/2013 | 2/22/2013 | P | PASS |
Tim Frost
|
|
|
*Re-assingned by Scott Arellano*
Robert Phone #: ###-####
|
INSP-Sprinkler Rough-in/Hydro | 1/7/2013 | 1/7/2013 | 1/7/2013 | P | PASS |
Troy Cobbley
|
|
|
The overhead hydro for 1st floor and rough to cover for 2nd floor passed. Sprinkler piping can be covered.
|
INSP-Sprinkler Rough-in | 1/4/2013 | 1/4/2013 | 1/4/2013 | P | FAIL |
Troy Cobbley
|
|
|
This was a tenting inspection. The tenting is still not secured to the trusses in many locations and can be easily moved. Piping is not approved for cover.
|
INSP-Sprinkler Rough-in/Hydro | 1/4/2013 | 1/4/2013 | 1/4/2013 | P | FAIL |
Troy Cobbley
|
|
|
Sprinkler rough-in for both floors passed but piping can not be covered on the second floor until the tenting has been repaired. Also the hydro test failed again.Starting presure was at 222psi and ended at 213psi.
|
INSP-Sprinkler Rough-in/Hydro | 1/2/2013 | 1/3/2013 | 1/3/2013 | P | PART |
Troy Cobbley
|
|
|
Todays inspection was for above ground hydro test. The second floor test passed. The first floor test failed due to a visable leak at the 1 1/2" cplg between the ball valve and ready riser.
|
INSP-Sprinkler Rough-in/Hydro | 12/31/2012 | 1/2/2013 | 1/2/2013 | P | CANC |
Troy Cobbley
|
|
|
This is an oh hydro Robert is the contact. Thanks Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 12/27/2012 | 12/31/2012 | 12/31/2012 | P | CANC |
Troy Cobbley
|
|
|
Robert is the contact. Thanks Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
|