INSP-Final Inspection | 3/6/2013 | 3/6/2013 | 3/7/2013 | P | PASS |
Forrest France
|
|
|
Fire sprinkler permit finaled.
|
INSP-Supply line flush | 3/6/2013 | 3/6/2013 | 3/7/2013 | P | PART |
Forrest France
|
|
|
UG fire supply line flush completed satisfactory.
|
INSP-Final Inspection | 3/5/2013 | 3/5/2013 | 3/5/2013 | P | PEND |
Forrest France
|
|
|
Final pending project related fire alarm permit work.
|
INSP-Sprinkler Rough-in/Hydro | 2/27/2013 | 2/27/2013 | 3/1/2013 | P | PART |
Forrest France
|
|
|
Overhead rough-in inspection completed. Need to add retainers on sidewall head piping below tanks, heads at the zone of influence near unit heaters to be correct temp rating per NFPA 13.
|
INSP-Sprinkler Rough-in/Hydro | 2/27/2013 | 2/27/2013 | 2/27/2013 | A | PART |
Forrest France
|
|
|
UG fire supply line hydrostatic testing passed.
|
INSP-Sprinkler Rough-in/Hydro | 2/19/2013 | 2/19/2013 | 2/21/2013 | P | PART |
Forrest France
|
|
|
Overhead hydrostatic testing completed satisfactory.
|
INSP-Sprinkler Rough-in/Hydro | 2/8/2013 | 2/8/2013 | 2/8/2013 | P | NH |
Forrest France
|
|
|
underground hydro - Don Phone #: ###-#### * No access to complete inspection.
|
INSP-Conference | 2/7/2013 | 2/7/2013 | 2/7/2013 | A | DONE |
Forrest France
|
|
|
Regarding hydrostatic testing
|
INSP-Conference | 1/30/2013 | 1/31/2013 | 1/31/2013 | A | DONE |
Troy Cobbley
|
|
|
Don requested that the FDC be moved from the 15th street side of th building to the north side alley. I contacted Tim Frost and it was determined that the FDC needs to remain on the 15th street side of the building but could be moved down the wall alittle.
|
INSP-Sprinkler Rough-in | 1/28/2013 | 1/29/2013 | 1/29/2013 | A | PART |
Forrest France
|
|
|
UG fire supply line thrust blocking verified,- okay to bury. Discussed seismic clearance at the ductile riser when floor slab is poured.
|
INSP-Sprinkler Rough-in | 1/28/2013 | 1/28/2013 | 1/28/2013 | P | NH |
Forrest France
|
|
|
No access to complete inspection.
|
INSP-Sprinkler Rough-in | 1/25/2013 | 1/25/2013 | 1/25/2013 | P | PART |
Forrest France
|
|
|
Ductile UG fire supply line stub-in and riser install verified. Discussed thrust blocking and joint restraint.
|