INSP-Final Inspection | 12/17/2013 | 12/17/2013 | 12/18/2013 | P | PASS |
Forrest France
|
|
|
|
INSP-Final Inspection | 12/12/2013 | 12/13/2013 | 12/13/2013 | A | PART |
Forrest France
|
|
|
C/N items include matched temp heads at an electrical room, replace hanger on added coverage, access to NW elevator machine room, floor drain function at the fire pump room.
|
INSP-Final Inspection | 11/27/2013 | 12/2/2013 | 12/3/2013 | A | PART |
Forrest France
|
|
|
Need to remove valves in the pressure sensing lines per NFPA 20, pump room still missing ventilation, floor drain does not function, final walkthrough at the basement incomplete.
|
INSP-Final Inspection | 11/19/2013 | 11/22/2013 | 11/26/2013 | A | NR |
Forrest France
|
|
|
Mike B is the contact. Thanks Phone #: ###-#### >> Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 10/8/2013 | 10/10/2013 | 10/10/2013 | A | PART |
Forrest France
|
|
|
Completed fire pump acceptance testing per NFPA 20. Noted fire pump room is missing required ventilation, floor drain does not function adequately, upright heads at the new west wall exceed min. distance from the wall.
|
INSP-Sprinkler Rough-in/Hydro | 3/27/2013 | 3/29/2013 | 3/29/2013 | P | PART |
Forrest France
|
|
|
For overhead hydrostatic testing of the header and supply piping.
|
INSP-Sprinkler Rough-in | 2/26/2013 | 2/27/2013 | 3/1/2013 | P | PART |
Forrest France
|
|
|
Noted corrections at the basement level shell work only.
|