INSP-Final Inspection | 12/17/2013 | 12/17/2013 | 12/18/2013 | P | PASS |
Forrest France
|
|
|
|
INSP-Final Inspection | 12/12/2013 | 12/13/2013 | 12/13/2013 | A | PART |
Forrest France
|
|
|
Incomplete ceilings, finishes and construction for shell work at the lobby and entry areas.
|
INSP-Final Inspection | 11/27/2013 | 12/2/2013 | 12/3/2013 | A | PART |
Forrest France
|
|
|
Need to relocate outside bell at the main street side above the correct FDC, 1st floor tenant work underway.
|
INSP-Final Inspection | 11/19/2013 | 11/22/2013 | 11/26/2013 | A | NR |
Forrest France
|
|
|
Mike B is the contact. Thanks Phone #: ###-#### >> Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 4/3/2013 | 4/3/2013 | 4/3/2013 | A | PART |
Forrest France
|
|
|
Reinspection for C/N items
|
INSP-Sprinkler Rough-in/Hydro | 3/27/2013 | 3/29/2013 | 3/29/2013 | P | PART |
Forrest France
|
|
|
1st floor shell protection hydrostatic test passed.
|
INSP-Sprinkler Rough-in | 2/26/2013 | 2/27/2013 | 3/1/2013 | P | PART |
Forrest France
|
|
|
Basement level only- not including the FP room
|
INSP-Sprinkler Rough-in | 2/28/2013 | 2/28/2013 | 3/1/2013 | A | PART |
Forrest France
|
|
|
Rough-in at the 1st floor level- ref. plans for annotations regarding corrections and adjustments to be made.
|