INSP-Final Inspection | 1/31/2013 | 2/1/2013 | 2/1/2013 | A | PASS |
Forrest France
|
|
|
Previous correction notice items verified for completion. Voltage monitor for the elevator shunt trip added while on site, as-builts recieved. Duct detectors and recall functions tested okay. Points map posted. Permit finaled.
|
INSP-Final Inspection | 1/29/2013 | 1/29/2013 | 1/29/2013 | P | FAIL |
Troy Cobbley
|
|
|
All fire pump devices were retested today and passed. Started to test the elevator recall and found that there are programing issues. We tried to test duct smoke detectors but found that some have not been wired for shutdown of the hvac units. Inspection to be rescheduled when the remaining items, as listed above, have been corrected and tested.
|
INSP-Final Inspection | 1/28/2013 | 1/28/2013 | 1/28/2013 | P | FAIL |
Troy Cobbley
|
|
|
Everything tested today except for the AES netcon needs to be retested. The signals sent to central station do not match what is being tested at the job site. Phase reversal and pump running are reversed. The manual pull station in the pump room is mounted too high.
|
INSP-Final Inspection | 1/25/2013 | 1/25/2013 | 1/25/2013 | P | CANC |
Troy Cobbley
|
|
|
Canceled due to time constraints. Brent Phone #: ###-####
|