INSP-Final Inspection | 5/3/2013 | 5/6/2013 | 5/6/2013 | A | PASS |
Forrest France
|
|
|
Final inspection completed 5/3. Permit finaled.
|
INSP-Sprinkler Rough-in | 2/21/2013 | 2/22/2013 | 2/22/2013 | A | PART |
Tim Frost
|
|
|
*Re-assingned by Scott Arellano*
Insulation rough in inspection approved.
Lonnie Phone #: ###-####
|
INSP-Sprinkler Rough-in | 2/14/2013 | 2/15/2013 | 2/15/2013 | A | PASS |
Troy Cobbley
|
|
|
Rough-in passed for the most part. Still need to have the riser installed, tenting verified and the sprinkler protection provided above the fire place. Piping can not be covered until tenting has been approved. I also went over the location of the outside alarm bell with the electrician.
|