INSP-Final Inspection | 5/20/2013 | 5/20/2013 | 5/20/2013 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled. Forward flush passed.
|
INSP-Sprinkler Rough-in/Hydro | 5/9/2013 | 5/10/2013 | 5/10/2013 | P | PASS |
Troy Cobbley
|
|
|
Wet system hydro test passed
|
INSP-Sprinkler Rough-in/Hydro | 5/8/2013 | 5/9/2013 | 5/9/2013 | A | PART |
Troy Cobbley
|
|
|
The underground and dry system hydro tests passed. The wet system failed again. The previous correction items have been addressed.
|
INSP-Sprinkler Rough-in/Hydro | 5/8/2013 | 5/8/2013 | 5/8/2013 | P | FAIL |
Troy Cobbley
|
|
|
Wet, dry and UG hydro tests failed due to visible drop in pressure on the guages.
|
INSP-Sprinkler Rough-in/Hydro | 3/14/2013 | 3/15/2013 | 3/15/2013 | P | FAIL |
Troy Cobbley
|
|
|
Hydro test of the wet system failed due to visable leakage at the drain weld on the riser. Earth quake bracing needs to be modifed as discussed and connected to the main piping instead of the lateral bracing. Plans need to be resubmitted showing the actual grid piping layout. We were unable to get the dry system to pump up to perform a hydro test. Rough-in inspection for the piping as installed passed.
|
INSP-Supply line flush | 3/11/2013 | 3/11/2013 | 3/11/2013 | P | PASS |
Troy Cobbley
|
|
|
Underground supply line flush passed
|
INSP-Supply line flush | 3/8/2013 | 3/8/2013 | 3/8/2013 | P | FAIL |
Troy Cobbley
|
|
|
United Water did not turn on the supply main so that we could perform the flush
|
INSP-Sprinkler Rough-in | 3/1/2013 | 3/1/2013 | 3/1/2013 | P | PART |
Forrest France
|
|
|
Remainder of UG fire supply line okay for cover.
|
FIR-Aging Inspection | 3/1/2013 | 3/1/2013 | 3/1/2013 | A | PART |
Troy Cobbley
|
|
|
The underground supply piping from the point of connection to the building foundation is ok to cover.
|