INSP-Final Inspection | 11/25/2013 | 11/25/2013 | 11/25/2013 | P | PASS |
Forrest France
|
|
|
Fire sprinkler permit work okayed for final. Need to provide signage at the new FDC's per plan review note. *To be finished prior to building permit final.
|
INSP-Sprinkler Rough-in/Hydro | 11/25/2013 | 11/25/2013 | 11/25/2013 | P | CANC |
Forrest France
|
|
|
Please call Perly 30 mins prior Phone #: ###-#### >> Inspection requested via web by Jacci Hunt Inspection cancelled from web by: Jacci Hunt
|
INSP-Final Inspection | 11/22/2013 | 11/22/2013 | 11/25/2013 | P | NR |
Forrest France
|
|
|
Inspection completed 11/22. Missing approved plans on site. Noted missing bracing and hanger at the east standpipe system addition.
|
INSP-Sprinkler Rough-in/Hydro | 11/18/2013 | 11/19/2013 | 11/19/2013 | P | PART |
Forrest France
|
|
|
Overhead hydrostatic test of new system piping completed and passed.
|
INSP-Supply line flush | 11/13/2013 | 11/14/2013 | 11/14/2013 | A | PASS |
Troy Cobbley
|
|
|
Underground lines flush on both sides of the building. Next inspection verify the check valve was changed to the correct direction.
|
INSP-Supply line flush | 11/12/2013 | 11/14/2013 | 11/13/2013 | P | CANC |
Forrest France
|
|
|
Please call Tyler 30 mins prior Phone #: ###-#### >> Inspection requested via web by Jacci Hunt Inspection cancelled from web by: Jacci Hunt
|
INSP-Supply line flush | 11/11/2013 | 11/13/2013 | 11/12/2013 | P | CANC |
Forrest France
|
|
|
Please schedule flush and call Tyler 30 mins prior Phone #: ###-#### >> Inspection requested via web by Jacci Hunt Inspection cancelled from web by: Jacci Hunt
|
INSP-Sprinkler Rough-in | 3/19/2013 | 3/20/2013 | 3/21/2013 | A | PART |
Forrest France
|
|
|
UG work okayed for cover at the south and north sides below floor slabs. Noted FDC's are installed approx. 15' from the structure- approved plans indicate 50'.
|