INSP-Final Inspection | 9/24/2013 | 9/25/2013 | 9/25/2013 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 9/23/2013 | 9/23/2013 | 9/23/2013 | P | CANC |
Troy Cobbley
|
|
|
Duplicate inspection
|
INSP-Final Inspection | 9/20/2013 | 9/23/2013 | 9/23/2013 | A | FAIL |
Troy Cobbley
|
|
|
The "well" needs to be installed at the FDC riser and provide tag for the backflow preventor and a head wrench.
|
INSP-Final Inspection | 8/20/2013 | 8/21/2013 | 8/21/2013 | A | FAIL |
Troy Cobbley
|
|
|
I stopped at the job site and found that the "well" has not been installed at the FDC as discussed. I also noted the signage at the bell is missing. I left Don a voice message.
|
INSP-Final Inspection | 8/1/2013 | 8/5/2013 | 8/5/2013 | P | CANC |
Troy Cobbley
|
|
|
don Phone #: ###-####
|
INSP-Supply line flush | 7/29/2013 | 7/29/2013 | 7/29/2013 | P | PASS |
Troy Cobbley
|
|
|
Underground flush passed
|
INSP-Sprinkler Rough-in/Hydro | 7/19/2013 | 7/22/2013 | 7/22/2013 | A | PASS |
Troy Cobbley
|
|
|
Overhead hydro test passed. I noted that the fire dept connection has not been installed on the street side of the building. I spoke with Don and he is going to contact Tim Frost to verify an approved location for the fdc and the electric alarm bell.
|
INSP-Supply line flush | 7/19/2013 | 7/22/2013 | 7/22/2013 | A | CANC |
Troy Cobbley
|
|
|
Cancel per Don Phone #: ###-####
|
INSP-Sprinkler Rough-in | 7/18/2013 | 7/19/2013 | 7/19/2013 | A | PASS |
Troy Cobbley
|
|
|
Rough-in now matches the plan modification.
|
INSP-Sprinkler Rough-in/Hydro | 4/29/2013 | 4/29/2013 | 4/29/2013 | P | FAIL |
Troy Cobbley
|
|
|
Due to extensive routing modifications, swing joints and additional sprinkler heads plan modifications will be needed for this project. Don is going to provide verification the pipe straps and screws are listed for hanging the 2" mains. Siesmic restraints are required for the branchlines. There is wood at the top of the old fire place so sprinkler protection as per the plans will be required. There appears to be an addtional combustible concealed space near the kitchen that will need sprinkler protection.
|
INSP-Sprinkler Rough-in/Hydro | 3/25/2013 | 3/27/2013 | 3/27/2013 | A | PASS |
Troy Cobbley
|
|
|
Todays inspection was an approval to cover the underground supply piping and an approval for the underground supply piping hydro test. I let Don know that as-builts showing the two additional 4" elbows will be required at the end of the project.
|