INSP-Final Inspection | 12/17/2013 | 12/17/2013 | 12/18/2013 | P | PASS |
Forrest France
|
|
|
|
INSP-Final Inspection | 12/12/2013 | 12/13/2013 | 12/13/2013 | A | PART |
Forrest France
|
|
|
C/N items on 16th floor and the penthouse level.
|
INSP-Final Inspection | 11/27/2013 | 12/2/2013 | 12/3/2013 | A | PART |
Forrest France
|
|
|
Noted a large non-sprinklered area above the 17th floor SE corner, remove foil at upright heads in the penthouse, provide access to the electrical room penthouse level for inspection, need signage at the control valve for the roof top hose connection, upright at the 16th floor service elevator lobby is blocked. 17th floor TI work underway.
|
INSP-Final Inspection | 11/19/2013 | 11/22/2013 | 11/26/2013 | A | NR |
Forrest France
|
|
|
Mike B is the contact. Thanks Phone #: ###-#### >> Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 7/30/2013 | 7/31/2013 | 7/31/2013 | A | PART |
Forrest France
|
|
|
OH hydrostatic test completed for the 16th and 17th floors.
|
INSP-Sprinkler Rough-in | 7/30/2013 | 7/31/2013 | 7/31/2013 | A | PART |
Forrest France
|
|
|
Preliminary rough-in inspection of the penthouse system only. Some areas incompleted or not yet constructed including the electrical room, top of stairway, south end duct, sheetrock at walls. Discussed possible obstructions.
|
INSP-Sprinkler Rough-in | 6/4/2013 | 6/6/2013 | 6/6/2013 | A | PART |
Forrest France
|
|
|
Shell system rough-in completed for the 16th and 17th floors. Noted five areas on the 17th floor and two areas on the 16th floor in need of revision- field changes to piping layout in the remote calc area on the 16th floor, floorplan change on the 17th floor SW corner, missing and obstructed heads at some locations, overspaced coverage at the mens restroom 17th floor. Coverage below ductwork incomplete at this time.
|