INSP-Final Inspection | 10/9/2013 | 10/10/2013 | 10/10/2013 | A | PASS |
Forrest France
|
|
|
Fire alarm permit finaled.
|
INSP-Alarm Testing | 10/9/2013 | 10/9/2013 | 10/9/2013 | P | PASS |
Forrest France
|
|
|
Completed remainder of alarm testing at the gatehouse including previous corrections and adjustment items. Override switch at the panel MP has been removed.
|
INSP-Alarm Testing | 10/8/2013 | 10/8/2013 | 10/9/2013 | P | FAIL |
Forrest France
|
|
|
Correction items incomplete at the time of requested inspection.
|
INSP-Alarm Testing | 10/8/2013 | 10/8/2013 | 10/8/2013 | A | PART |
Forrest France
|
|
|
|
INSP-Final Inspection | 10/1/2013 | 10/4/2013 | 10/4/2013 | P | PART |
Forrest France
|
|
|
Completed fire alarm testing for buildings 5,6,7, 12 and 14. Reinspection for ADA room 1013, room number changes, and programing at buildings 5-7 also completed.
|
INSP-Final Inspection | 9/30/2013 | 10/1/2013 | 10/1/2013 | A | PART |
Forrest France
|
|
|
Completed fire alarm testing for buildings 8, 9, 10, and 11. Also finished reinspection for previous correction items at building 4. Correction and adjustment items noted today include; non-functional visual notification at ADA unit 1013, plans show incorrect room numbers for FACP units in buildings 6 and 9, MP stations for panel at buildings 5,6, and 7 did not activate horn strobes.
|
INSP-Alarm Testing | 9/30/2013 | 9/30/2013 | 9/30/2013 | P | NR |
Forrest France
|
|
|
Pending noted corrections at building #4
|
INSP-Final Inspection | 9/27/2013 | 9/27/2013 | 9/27/2013 | P | FAIL |
Troy Cobbley
|
|
|
Todays inspection was for Building #4. See the city approved plans for corrections required.
|
INSP-Alarm Testing | 9/26/2013 | 9/26/2013 | 9/26/2013 | P | PART |
Forrest France
|
|
|
Fire alarm testing completed for buildings 1,2 and 3.
|
INSP-Final Inspection | 9/24/2013 | 9/25/2013 | 9/26/2013 | P | FAIL |
Forrest France
|
|
|
Gatehouse system inspection items inlcude; provde H/S at the workshop, SD at the 1st floor office needs relocated away from the HVAC diffuser, change descriptor at the 2nd floor SD storage room, alarm verification feature appears to be enabled for system smokes, panel map needs to include initiating device locations per review note #26, provide knox box per review comment #27, need FD approval for the toggle switch at the main panel MP. HD not tested at this time. Notification appliances and manual pull stations tested okay.
|
INSP-Conference | 5/15/2013 | 5/16/2013 | 5/16/2013 | P | DONE |
Forrest France
|
|
|
On site conference with contractor regarding fire alarm permit work, NFPA 72 requirements, plan review comments, field conditions, project schedule, etc.
|