Permit Information
Permit NumberFIR13-00184
StatusFinaled
Name PHOENIX FIRE PROTECTION
Site Address 8055 W GODDARD RD
Project NameCapital High School Hallway Re
Customer Number 
ePlanReviewYes
Description
The fire sprinkler scope of work consists of providing partial fire protection and stub ins for future use.

Plan Mod #1 – 8/15/2013
Pipe routing modifications due to field changes
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection8/22/20138/22/20138/22/2013PPASS
DetailsTroy Cobbley
Permit finaled
INSP-Sprinkler Rough-in/Hydro8/7/20138/13/20138/13/2013APASS
DetailsTroy Cobbley
It took two inspections but the overhead hydro passed.
INSP-Sprinkler Rough-in8/5/20138/6/20138/6/2013PPASS
DetailsTroy Cobbley
Todays inspection verified that the seismic bracing had been installed on the gridded system in the Cafeteria. This included the branchlines and the far main.
INSP-Sprinkler Rough-in8/1/20138/5/20138/5/2013PPART
DetailsTroy Cobbley
Todays inspection was for the remaining first floor east corridor which has not been connected but is ok to cover. Also todays inspection was for the cafeteria which was already covered. Seismic bracing is missing on the branch lines and the 1 1/2" far main. Also the pipe routing has been modified for the branchlines and the new arm overs to the pendant heads. Plan modifications are required showing all of these changes and all of the other piping changes through-out the new system. Include the sprinkler heads model changes and revised hydraulic calculations.
INSP-Sprinkler Rough-in8/1/20138/5/20138/1/2013PCANC
DetailsTroy Cobbley
We need a 1st floor inspection. Please call Bruce 30 mins prior. Phone #: ###-#### >> Inspection requested via web by Jacci Hunt Inspection cancelled from web by: Jacci Hunt
INSP-Sprinkler Rough-in/Hydro7/26/20137/29/20137/29/2013PPASS
DetailsTroy Cobbley
See the city approved plans for the first floor areas where the sprinkler piping is ok to cover. Plan modifications may be needed showing the different sprinkler pendants installed and pipe routing changes. Contractor needs to have a conversation with the sprinkler plan reviewer to get a resolution.
INSP-Sprinkler Rough-in7/15/20137/16/20137/16/2013PPART
DetailsTroy Cobbley
RTC 2nd floor is mostly ok. Contractor needs to get with plan review but it appears a plan modification is needed since viking pendants were installed instead of tyco. Also the earthquake bracing has not been installed as shown on the plans. I'm ok with the second floor lay-in tile being installed in all locations except where I will need to view earth quake bracing.
INSP-Sprinkler Rough-in6/10/20136/11/20136/11/2013ACANC
DetailsTroy Cobbley
troy or joe @ ###-#### Phone #: ###-####