Permit Information
Permit NumberFIR13-00214
StatusFinaled
Name TREASURE VALLEY FIRE PROTECTION
Site Address 450 E GOWEN RD
Project NameCommercial Tire
Customer Number 
ePlanReviewYes
Description
The fire sprinkler scope of work consists of providing an ESFR system for a tire retread plant and warehouse. The storage height will not exceed 25’ in a 30’ high building. The system is a 6”x6”x3” grid with a 6” center rail. The wet system also protects a two-story office area in the SE corner of the building. In addition, to the wet system there is dry system protecting a truck canopy area. The dry system is side feed with a 4” main and 2” lines. The new 8”x308’± C-900 supplies an 8” backflow preventer and 8” header.

NOTE: The truck canopy, office area and truck shop are not designed to permit the display or storage of tires in the excess of a 5’ height.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection8/12/20138/12/20138/13/2013PPASS
DetailsForrest France
Fire sprinkler permit approved for final status.
INSP-Final Inspection8/7/20138/12/20138/12/2013APART
DetailsForrest France
Completed trip testing, forward flow and final walkthrough.
INSP-Supply line flush8/5/20138/7/20138/7/2013APART
DetailsForrest France
UG fire supply line flush completed satisfactory.
INSP-Sprinkler Rough-in7/24/20137/24/20137/26/2013PPART
DetailsForrest France
Okay to cover grid ceilings at the 1st and 2nd floors.
INSP-Sprinkler Rough-in/Hydro7/25/20137/26/20137/26/2013APART
DetailsForrest France
Overhead rough-in at the grid ceilings SW corner approved for cover. Also completed overhead hydrostatic test of the new wet system.
INSP-Sprinkler Rough-in/Hydro7/16/20137/17/20137/17/2013APASS
DetailsTroy Cobbley
24 hour air test passed
INSP-Sprinkler Rough-in/Hydro7/15/20137/16/20137/16/2013APART
DetailsForrest France
Begin 24 hr air test of the new dry system at 10:30 AM @ 47psig.
INSP-Sprinkler Rough-in7/15/20137/15/20137/15/2013PPASS
DetailsTroy Cobbley
Todays inspection was a rough-in for the whole system. See locations circled in red where the sprinkler protection at the unit heaters has not been installed. Per Tim the EFSR heads located under/in the smoke vents are ok more than 18" from the deck. Per the drawings no earth quake bracing/retaining straps are required and none are installed. I did not look at the riser. The overhead hydro test of the dry system passed. A plan modifiction is required for the piping changes in the north office area and the heads under the overhead doors.
INSP-Sprinkler Rough-in6/17/20136/17/20136/17/2013PPART
DetailsForrest France
Remainder of UG fire supply line to the point of connection at the PL okayed to cover-
INSP-Sprinkler Rough-in6/4/20136/5/20136/6/2013PPART
DetailsForrest France
UG fire supply line to a point 100' from the stem wall okayed for bury as marked on approved plans (90 ell not included).