INSP-Final Inspection | 9/23/2013 | 9/24/2013 | 9/25/2013 | P | PASS |
Forrest France
|
|
|
Reinspection completed satisfactory. First floor dry system trip test passed after corrections made.
|
INSP-Sprinkler Rough-in/Hydro | 9/11/2013 | 9/12/2013 | 9/12/2013 | P | FAIL |
Forrest France
|
|
|
Time limitations per NFPA 13 for dry system water delivery were exceeded for the 1st floor system.
|
INSP-Sprinkler Rough-in/Hydro | 9/11/2013 | 9/12/2013 | 9/12/2013 | A | PART |
Forrest France
|
|
|
Completed hydrostatic testing of the new dry system piping at the 4th, 5th floors, and riser.
|
INSP-Sprinkler Rough-in/Hydro | 9/5/2013 | 9/9/2013 | 9/12/2013 | P | PART |
Forrest France
|
|
|
Completed acceptable fire pump testing per NFPA 20 guidelines.
|
INSP-Sprinkler Rough-in/Hydro | 9/11/2013 | 9/11/2013 | 9/12/2013 | P | PART |
Forrest France
|
|
|
Completed satisfactory hydrostatic testing for the new dry system piping at the 1st, 2nd, and 3rd, floors. Also verified previous correction items are finished or underway.
|
INSP-Sprinkler Rough-in/Hydro | 9/9/2013 | 9/10/2013 | 9/11/2013 | P | NR |
Forrest France
|
|
|
Hydro for systems Phone #: ###-#### >> Inspection requested via web by John Venche
|
INSP-Sprinkler Rough-in/Hydro | 8/30/2013 | 9/5/2013 | 9/6/2013 | A | NR |
Forrest France
|
|
|
|