INSP-Final Inspection | 8/5/2015 | 8/6/2015 | 8/6/2015 | P | PASS |
Jim Page
|
|
|
Pump installed dedicated to the fire system, fire sprinkler inspection passed/complete
|
INSP-Final Inspection | 3/17/2014 | 3/18/2014 | 3/20/2014 | P | PASS |
Forrest France
|
|
|
Fire sprinkler permit finaled.
|
INSP-Final Inspection | 2/5/2014 | 2/6/2014 | 2/5/2014 | A | CANC |
Forrest France
|
|
|
jonathan Phone #: ###-#### // cancelled per Jonothan, will call back to reschedule 2/5/14 leg
|
INSP-Final Inspection | 10/21/2013 | 10/21/2013 | 10/21/2013 | P | PART |
Forrest France
|
|
|
Tenting reinspection complete.
|
INSP-Sprinkler Rough-in | 10/17/2013 | 10/18/2013 | 10/18/2013 | A | FAIL |
Forrest France
|
|
|
Tenting at four areas in need of adjustment- main entry, laundry room, and two locations in the garage.
|
INSP-Sprinkler Rough-in | 10/17/2013 | 10/17/2013 | 10/18/2013 | P | NR |
Forrest France
|
|
|
jonathan - verify tenting Phone #: ###-#### *Noted several areas in need of adjustment to provide adequate cold cavity protection.
|
INSP-Sprinkler Rough-in | 10/7/2013 | 10/7/2013 | 10/7/2013 | P | PART |
Troy Cobbley
|
|
|
Need approved as-builts on site to verify approved installation. Need sprinkler coverage modified , as marked on plans, near kitchen and a lintel or additional head in the main floor northwest bathroom/shower. No piping can be covered until a tenting inspection is requested and passed.
|
INSP-Sprinkler Rough-in | 8/6/2013 | 8/6/2013 | 8/6/2013 | P | PART |
Forrest France
|
|
|
UG fire supply line from the point of connection at the street to the stem wall okayed for bury.
|