Description
The fire sprinkler scope of work consists of replacing black piping after the dry valves with galvanized piping due to deterioration. The pump and header are existing and are not being revamped.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection9/19/20139/20/20139/20/2013APASS
DetailsForrest France
C/N items finished. Reinspection passed. Fire sprinkler permit finaled.
INSP-Final Inspection9/18/20139/19/20139/19/2013ACANC
DetailsForrest France
Need trip test and Final sprinkler system inspection. Please contact Richard Clark ###-#### for questions. Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
INSP-Sprinkler Rough-in9/12/20139/13/20139/13/2013APART
DetailsForrest France
Remainder of C/N items verified for completion. System two trip tested at 1 min. 6 seconds. System one trip tested at 2 min 15 sec. and will require the addition of a QOD. Quick trip of the new dry valve passed.
INSP-Sprinkler Rough-in9/11/20139/12/20139/12/2013APART
DetailsForrest France
Items on the previous correction notice are not yet finished at some locations including ssu's at the ramp, missing seismic brace, missing section of galv pipe, trapped outlet. Verified missing coverage has been added, hangers adjusted, head cages on, adjustments, etc. are finished. New valve and trim monitoring not yet finished. Discussed trip test schedule.
INSP-Sprinkler Rough-in/Hydro8/29/20138/30/20138/30/2013APART
DetailsForrest France
Completed hydrostatic testing of the new dry system piping serving the north half of the parking garage. Also finished systems walkthrough and noted items in need of revision, adjustment or repair including missing or overspaced upright protection at four locations, duct and hanger obstructions, three sprigs too far below the deck, one missing EQ brace, one trapped outlet, provide head cage at SW head, one section of 3" main is not yet replaced with galv. Ref. annotations on plans.
INSP-Sprinkler Rough-in/Hydro8/27/20138/29/20138/29/2013PPART
DetailsForrest France
Completed hydrostatic testing of the new dry system serving the south half of the parking garage.