INSP-Final Inspection | 1/2/2014 | 1/8/2014 | 1/8/2014 | P | PASS |
Troy Cobbley
|
|
|
Permit finled. Underground flush passed.
|
INSP-Supply line flush | 11/25/2013 | 11/25/2013 | 11/25/2013 | P | PASS |
Troy Cobbley
|
|
|
Underground flush passed
|
INSP-Supply line flush | 11/21/2013 | 11/22/2013 | 11/22/2013 | P | CANC |
Troy Cobbley
|
|
|
Cancel per James
|
INSP-Supply line flush | 11/21/2013 | 11/21/2013 | 11/21/2013 | P | CANC |
Troy Cobbley
|
|
|
United Water did not turn on the underground supply line. Will need to reschedule.
|
INSP-Sprinkler Rough-in/Hydro | 11/11/2013 | 11/12/2013 | 11/12/2013 | P | PASS |
Troy Cobbley
|
|
|
The overhead hydro passed. Tenting passed. Piping can be covered. Two pendants on the first floor need to be relocated so as no to be more than 10' from any one wall. These heads will be checked at the final per discussion.
|
INSP-Sprinkler Rough-in/Hydro | 8/26/2013 | 8/27/2013 | 8/27/2013 | A | PASS |
Troy Cobbley
|
|
|
Inspection was for a cover of the underground piping. Piping can be covered. 2" poly like the others.
|