INSP-Final Inspection | 10/24/2013 | 10/25/2013 | 10/25/2013 | A | PASS |
Craig D. Hanson
|
|
|
System pass and in service. CDH
|
INSP-Final Inspection | 10/23/2013 | 10/23/2013 | 10/23/2013 | P | CANC |
Troy Cobbley
|
|
|
Cancel per Mike Rogers
|
INSP-Sprinkler Rough-in | 9/18/2013 | 9/18/2013 | 9/18/2013 | P | PASS |
Troy Cobbley
|
|
|
Rough-in inspection passed. Piping can be covered. One head adjusted while I waited. Underground supply line flushed passed.
|
INSP-Supply line flush | 9/12/2013 | 9/13/2013 | 9/13/2013 | A | CANC |
Troy Cobbley
|
|
|
United Water still has not turned on the underground supply water
|
INSP-Sprinkler Rough-in/Hydro | 9/12/2013 | 9/13/2013 | 9/13/2013 | A | PASS |
Troy Cobbley
|
|
|
The overhead hydro for both floors passed
|
INSP-Supply line flush | 9/11/2013 | 9/12/2013 | 9/12/2013 | A | FAIL |
Troy Cobbley
|
|
|
United water has not turned on the water supply yet
|
INSP-Sprinkler Rough-in/Hydro | 9/11/2013 | 9/12/2013 | 9/12/2013 | A | CANC |
Troy Cobbley
|
|
|
The underground hydro passed
|
INSP-Sprinkler Rough-in | 8/7/2013 | 8/8/2013 | 8/8/2013 | P | PASS |
Troy Cobbley
|
|
|
The 2" poly supply piping is ok to cover
|