INSP-Final Inspection | 12/10/2013 | 12/10/2013 | 12/10/2013 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 11/19/2013 | 11/20/2013 | 11/20/2013 | A | PART |
Troy Cobbley
|
|
|
A temporary occupancy is being given, with fire dept approval, until this permit is complete. Work needing done is ceiling tile installed in the HC Company tenant space and minor items on the fire sprinkler riser. Forward flush test passed inspection.
|
INSP-Final Inspection | 11/19/2013 | 11/19/2013 | 11/19/2013 | P | FAIL |
Troy Cobbley
|
|
|
Not ready for a final inspection yet. However all sprinkler piping in the HC Company tenant space can be covered (rough-in passed). Overhead hydro test passed.
|
INSP-Sprinkler Rough-in | 10/9/2013 | 10/9/2013 | 10/9/2013 | P | PART |
Troy Cobbley
|
|
|
In general the rough-in passed. Noted missing retaining straps and a couple of earth quake braces. As-builts will be needed showing the changes in the main routing near the riser and the deletion of one of the 2" branchlines.
|