Permit Information
Permit NumberFIR13-00402
StatusFinaled
Name JBL FIRE PROTECTION LLC
Site Address 10115 W SMOKE RANCH DR
Project NameUnion Square Phase 2 Bldg 13
Customer Number 
ePlanReviewYes
Description
The fire sprinkler scope of work consists of protecting a new 3 level residential building per NFPA 13R

To construct a wood frame, Three story, 20,412 sq. ft., 18 Unit Multi Family Dwellings All units exceed 800 sq. ft., are fully sprinklered W/ alarm. Work includes associated site work, footing & foundation, structural & non-structural framing; electrical, mechanical, plumbing, sprinkler & alarm work; fire-resistive construction between units, at stair enclosures or rated corridor breezeways; accessible Type 'A' & 'B' units; interior cabinetry, wall, floor and ceiling finishes and fixtures. All work shall comply with the approved drawings, the plan review report, and all applicable codes. This building will be fire sprinkled with a 13R sprinkler system. **SRZ** DRH13-00005 CUP12-00064
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection3/28/20143/31/20143/31/2014PPASS
DetailsTroy Cobbley
Permit finaled
INSP-Sprinkler Rough-in/Hydro3/12/20143/12/20143/12/2014PPASS
DetailsTroy Cobbley
Hydro test passed
INSP-Sprinkler Rough-in/Hydro2/5/20142/7/20142/6/2014ACANC
DetailsTroy Cobbley
overhead - jonathan Phone #: ###-#### // cancelled per Jonothan at JBL, will call back to reschedule 2-6-14 leg
INSP-Sprinkler Rough-in12/2/201312/2/201312/2/2013PPASS
DetailsTroy Cobbley
Dry head installation and tenting verified. Piping can be covered.
INSP-Sprinkler Rough-in11/22/201311/22/201311/22/2013PPASS
DetailsTroy Cobbley
Overhead rough-in passed. Still need tenting inspection, heat tape inspection and the dry sidewalls for the second and third floors