INSP-Final Inspection | 12/26/2013 | 12/26/2013 | 12/26/2013 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 12/9/2013 | 12/10/2013 | 12/10/2013 | A | FAIL |
Troy Cobbley
|
|
|
All notification devices were tested today. Some corrections/additions/relocations are needed and have been identified on the city approved plans. Need correct batteries installed in the FACP, verify supervision of NAC panels, verify a/v's in pharmacy, need access controled egress doors connected to the facp, verify interconnection with the pre-action panel and need as-builts.
|
INSP-Conference | 9/23/2013 | 9/23/2013 | 9/23/2013 | P | DONE |
Troy Cobbley
|
|
|
Brian and I went over review comments and other misc items
|