INSP-Final Inspection | 5/15/2014 | 5/16/2014 | 5/16/2014 | A | PASS |
Craig D. Hanson
|
|
|
|
INSP-Sprinkler Rough-in | 2/6/2014 | 2/6/2014 | 2/6/2014 | P | PART |
Forrest France
|
|
|
Okay for ceiling cover.
|
INSP-Final Inspection | 2/5/2014 | 2/5/2014 | 2/5/2014 | P | PART |
Forrest France
|
|
|
Overhead work approved for cover- plan modification verified.
|
INSP-Sprinkler Rough-in | 2/3/2014 | 2/3/2014 | 2/3/2014 | P | FAIL |
Forrest France
|
|
|
Approved plans indicate a max. spacing of 16x16- Noted five locations overspaced at 9' from adjacent walls. Also need to verify materials in contact with CPVC piping are compatible per the mfg. listing such as fire caulk, duct mastic, and cables.
|
INSP-Sprinkler Rough-in | 1/24/2014 | 1/27/2014 | 1/27/2014 | A | NR |
Forrest France
|
|
|
Need to provide plan modification for resubmittal due to significant changes in the installation from original approved drawings. No approval for cover at this time.
|
INSP-Conference | 11/5/2013 | 11/5/2013 | 11/5/2013 | A | DONE |
Forrest France
|
|
|
Regarding revised calculations for field changes.
|
INSP-Sprinkler Rough-in | 11/4/2013 | 11/4/2013 | 11/5/2013 | P | PART |
Forrest France
|
|
|
UG fire supply line from the point of connection at the street to the stub-in okayed pending revised pipe size to 1 1/2" and elevation gain are included in the calcs. Need to ensure adequate cover (min. bury of 4'-6") is provided at the SW corner of the house near the patio and retainer wall section as discussed.
|