Permit Information
Permit NumberFIR13-00618
StatusFinaled
Name SHILO AUTOMATIC SPRINKLER CO
Site Address 423 N MITCHELL ST
Project NameRSD Warehouse
Customer Number 
ePlanReviewYes
Description
The fire sprinkler scope of work consists of providing a new wet system for an office warehouse. The warehouse area is divided into two tenants. A new 6” C-900 underground main will supply the system. There is a 6 header equipped with a 6” backflow preventer and 6” riser manifold. The warehouse area is design as a 4”x3”x2” grid. The mercantile/office area is supply by the primary main with a side feed type system. ELO sprinklers are being utilized in the warehouse area.

Refrigeration Supplies Distributor - Tenant Improvement - To finish an approximately 21,000 square foot tenant space within a new 25,900 square foot shell building. The new tenant space will be located on the east side of the new shell building and will include a showroom, part supply, offices, training room, and warehouse space for Refrigeration Supplies Distributor (Tenant A). This permit also includes related interior fit & finish, mechanical, electrical & plumbing as required for a finished tenant space
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection5/29/20145/30/20145/30/2014APASS
DetailsTroy Cobbley
Permit finaled
INSP-Final Inspection5/21/20145/22/20145/22/2014PFAIL
DetailsTroy Cobbley
Provide re-submittals as previously discussed. Forward flush passed and final rough-in inspection for the office area passed.
INSP-Sprinkler Rough-in/Hydro4/21/20144/22/20144/22/2014APASS
DetailsTroy Cobbley
Overhead hydro test passed.
INSP-Sprinkler Rough-in3/25/20143/27/20143/27/2014PPASS
DetailsTroy Cobbley
Overhead rough-in passed. Will need a cover inspection once the pendant heads in the office area are installed. It appears that branchline restraints will be required and the combustible concealed space at the front entrance will need addressed. Mike stated that they are resubmitting showing the column protection and the relocation of the east main (office area).
INSP-Supply line flush3/20/20143/21/20143/21/2014PPART
DetailsForrest France
UG fire supply line flush completed satisfactory.
INSP-Sprinkler Rough-in/Hydro3/14/20143/14/20143/14/2014PPASS
DetailsTroy Cobbley
The ug hydro passed
INSP-Sprinkler Rough-in2/21/20142/24/20142/25/2014PPART
DetailsForrest France
UG fire supply line including the IBR approved for bury.