INSP-Final Inspection | 3/21/2014 | 3/21/2014 | 3/21/2014 | P | PASS |
Forrest France
|
|
|
Fire sprinkler permit finaled.
|
INSP-Final Inspection | 3/20/2014 | 3/21/2014 | 3/21/2014 | A | PART |
Forrest France
|
|
|
Completed satisfactory air testing of the new dry system per NFPA 13 within allowable pressure loss at the guage.
|
INSP-Sprinkler Rough-in | 3/20/2014 | 3/20/2014 | 3/20/2014 | P | PASS |
Troy Cobbley
|
|
|
Started 24 hr air test at 10:30 with 52 psi on the guage.
|
INSP-Final Inspection | 3/18/2014 | 3/19/2014 | 3/19/2014 | A | FAIL |
Troy Cobbley
|
|
|
Not ready for a final yet. Overhead hydro passed. Forward flush passed. Trip test of 28 seconds passed. Rough-in inspection for concealed area passed. Missing seismic brace provided. Signal test of tampers and pressure switches passed. Still need the 24 hour air test.
|
INSP-Sprinkler Rough-in | 3/3/2014 | 3/3/2014 | 3/3/2014 | P | PASS |
Troy Cobbley
|
|
|
Rough-in passed. Missing one earth quake brace and need access to the above ceiling areas as discussed.
|