Permit Information
Permit NumberFIR13-00639
StatusFinaled
Name ABSOLUTE FIRE PROTECTION
Site Address 1879 S CENTURY WAY
Project NameWestern Recyling
Customer Number 
ePlanReviewYes
Description
The fire sprinkler scope of work consists of 6” underground supply through a 6” backflow preventer to (2) Dry Systems and (2) Wet systems. Each longitudinal half of the production area is protect by a side feed dry system. There is a side feed system protecting the loading dock. The loading dock protection is supplied by one of the dry systems. The two story office area is protected with a wet system for each floor. The production area is a recycling plant, recycling - aluminum, paper and plastics. The recycling plant and dock is design for ordinary hazard group II. The office area is light hazard.

FIELD INSPECTOR: There is a lot of processing equipment on this project. Undoubtedly, there will be obstructions greater than 48”, which will require additional sprinklers. Please, do not final this project until all equipment has been installed and all obstructions have proper fire protection.

Plan Mod#1 – 8/12/2014
Fire protection is being added below the sorting equipment in areas that are over 4' wide. Some areas on the east side have two layers of conveyors over 4' wide with sprinklers below both. The stairs, most of the catwalks and many conveyors are less than 4' wide and do not have sprinklers below. There are many low point drains due to the owner's request, to have the main high and drop down to lines. Most drains are 1/2" valve w/plug (less than 5 gal. trapped). Some have drum drip assemblies. The 3” main & branch lines under the main body of the equipment are sized like the existing loading dock piping. Drops to the east side & conveyor pits are sized like the production area roof system piping, seven sprinklers from a 2” feed.

Western Recycling - New Production Warehouse - To construct a new 37,595 square foot, one story, pre-engineered metal warehouse building with a 1,820 square foot unfinish mezzanine for future office space. A separate tenant improvement permit will be required to finish the mezzanine as an office occcupancy. All construction per the approved plans and attached comment list. JCM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection8/27/20148/28/20148/28/2014APASS
DetailsTroy Cobbley
24 hour air test passed and earth quake bracing has been added. Permit finaled
INSP-Sprinkler Rough-in/Hydro8/26/20148/27/20148/27/2014APART
DetailsTroy Cobbley
24 hour air test started at 9:00am with pressure marked on guage. Roughin on second pit and piping under equipment passed except it appears a longitudinal bracing is missing on the 3" main.
INSP-Sprinkler Rough-in/Hydro8/21/20148/22/20148/22/2014PPASS
DetailsTroy Cobbley
Overhead 200lb hydro test passed for both systems. Rough-in passed for east garbage/conveyor pit.
INSP-Final Inspection5/8/20145/9/20145/9/2014APART
DetailsTroy Cobbley
All corrections have been completed and the forward flush passed. Can not final this permit until possible modifications have been performed due to equipment being installed.
INSP-Final Inspection5/7/20145/8/20145/8/2014PFAIL
DetailsTroy Cobbley
Need forward flush, 911 sticker and zone map to finish. All alarm devices tested ok. Siesmic bracing has been installed.
INSP-Sprinkler Rough-in/Hydro5/5/20145/6/20145/6/2014APASS
DetailsTroy Cobbley
The 24 hour air test passed for both dry systems.
INSP-Sprinkler Rough-in/Hydro5/2/20145/5/20145/5/2014APASS
DetailsTroy Cobbley
The 24 hour air test was started at 8:00 am with the pressure guages marked in red for both north and south dry systems.
INSP-Sprinkler Rough-in/Hydro5/1/20145/1/20145/1/2014PPASS
DetailsTroy Cobbley
Overhead hydro on all four systems passed.
INSP-Supply line flush4/28/20144/29/20144/29/2014PPASS
DetailsTroy Cobbley
Underground Flush passed. Also performed a rough-in and found that the only real issue other than final inspection items is the lack of seismic bracing on all of the branchlines. Per the plans the piping was to be installed without per the exception of chapter 9 but was run at a lower elevation.
INSP-Supply line flush4/28/20144/28/20144/28/2014PPASS
DetailsTroy Cobbley
Underground hydro passed
INSP-Sprinkler Rough-in3/27/20143/28/20143/28/2014PPASS
DetailsTroy Cobbley
Mens and womens restroom piping is ok to cover. Also piping under the stair landing is ok to cover.
INSP-Supply line flush11/25/201311/26/201311/26/2013APART
DetailsCraig D. Hanson
Underground rough to cover only, no hydro or flush. pass.